Work is progressing on programme at our Hampton site

Published on Wednesday 6 February 2019

We are currently carrying out the design and build of a ground floor retail unit and 8 flats over 2 more floors on our site in Hampton, Peterborough.

The roof structure has been installed and the roofing contractor has started to install the roof coverings. The external masonry facade has almost reached eaves level and the external windows and doors have been installed. Internal metal stud walls have been constructed and 1st fix electrics and plumbing to the first floor is complete, allowing the plastering to commence.

The scaffold is due to be struck in 4 weeks so the external works and drainage can resume. The project is still on course to complete in June 2019.