New contract awarded for the Design and Build of 27 dwellings

Published on Monday 6 April 2020

We are pleased to announce we have been awarded a contract to design and build 27 new dwellings for Cross Keys Homes in Elm, near Wisbech. The foundation design for the houses consists of 17m deep pre-cast concrete piles and reinforced concrete ground beams, which will then support a masonry footings and a thermal block and beam floor. From the ground floor upwards the houses will be constructed using pre-fabricated timber frame units with a brickwork external skin in order to reduce time on site and make the construction process more efficient. The houses are due for completion in September 2021.