Estate road being formed on site of 27 affordable houses

Published on Friday 11 September 2020

Over the last 6 weeks the adoptable sewers have been laid and private estate road constructed on our site to design and build 27 houses in Elm. Some of the sewers are up to 375mm in diameter and have now all been connected to the private lateral drains. The road has now been excavated to formation level and the sub-base is being laid ready to receive the mains incoming services later this month.

Once the tarmac is laid the site will be ready to receive their first delivery of timber frames which will commence the highly anticipated superstructure element of the project.