After a difficult few months the windows and doors have finally been installed at our project in Ropsley to design and build a new village hall. This has allowed internal works to start which began with first fix trades and a bird cage scaffolding being erected in the main hall to install the acoustic plasterboard ceiling.

Plastering work to the remaining building is underway and second fix trades have been booked in to follow. Groundworks will be re-commencing in July to get the sewer connection complete and external slabbing and outstanding drainage installed.

The project is still on programme to complete in September 2020.