Masonry work commences at 12 dwellings site in Newton

Published on Friday 14 March 2014

Substructure works are nearing completion as masonry work commences across the busy 12 houses site at Newton, Wisbech. So far we’ve battled through the very wet site to finish the piling and installation of the pre-cast ground beams. We’re currently installing the blockwork to beam seating level to allow installation of the structural block and beam floors.

The project is for Roddons Housing Association and is due for completion late in the year.