Piling works complete at Elm

Published on Thursday 4 June 2020

After a challenging few months, our project to design and build 27 new dwellings for Cross Keys Homes is well under way.

The piling works were complete a week and a half ahead of programme in a bid to minimise disruption to the neighbouring properties.

Excavation for the reinforced ground beams has commenced with the below ground masonry due to follow shortly after.

All of the trades are pulling together to meet the clients critical golden brick date of 31st July.