Plastering works have started on 16 new dwellings

Published on Wednesday 11 November 2020

Works are progressing well on our site in Wicken. Plots 1-6 are awaiting the windows to be fitted whilst plots 11, 12, 15 and 16 are being plastered. Plots 13 and 14 are the most advanced as the walls have been mist coated, the kitchens have been installed and the skirting, architrave and internal doors are all fitted. The second fix mechanical and electrical is on going to these plots with a view to be completed within the next couple of weeks. Externally our ground workers are finalising the on site drainage and preparing to start the hard landscaping works to the rear of the advanced plots. Off site the management team are working tirelessly to get the sectional agreements in place so we can begin the off site works to the highways to the adjacent road