Progression of works at St Ives

Published on Friday 1 May 2020

Works are progressing in earnest on our site in St Ives as we are closing in on the contract completion date. 

Second fix works have commenced to two of the 3 blocks with the completion of kitchens, internal doors, stairs and floor coverings. Sanitary ware had been installed to bathrooms and en-suites and the wall and floor tiling has also been completed to these blocks.

External works are also making good progress with the completion of the drainage connection in the road in time for Easter Weekend. Onsite foul and surface water drainage has now been completed. Foundations have been installed for the garden walls with brickwork commencing this week.