Ropsley Village Hall gets closer to completion

Published on Monday 10 August 2020

As the final phase of our project to design and build the new Ropsley Village Hall continues, the internal works are progressing with the doors and kitchens being fitted ready to receive the new vinyl floor coverings. All internal surfaces have been decorated including a feature wall in each room as requested by the client.

Externally, the foul water sewer connection is now complete and the last drainage is being installed on site. The hard landscaping is underway with the slabs being laid to form an access path around the building.
 

As we enter the last six weeks of the programme we are still due to finish on time and within the clients budget.