Wothorpe Steelwork

Published on Friday 10 July 2020

Facing bricks and Structural Steel have arrived on site this week having been delayed through the current Pandemic situation. We are now able to carry on with the superstructure. The steelwork has been the subject of submitting and approving details and because there are sections that are fixed down to the foundations this limited the amount of work that could be carried out. Likewise, we are using the Linear Range bricks up to plinth level and due to plants being shut down and staff being furlouged, these bricks were no longer available. Fortunately, we have now managed to source enough for our requirements and we will be able, at long last, make meaningful progress.